How the work is tracked: an epic per machine, and a roadmap in git
Until today the open issues were a flat list. A machine’s missing parts, a flaky browser check, a speed figure and a 3D model’s failed check all sat side by side, and several loose ends lived only in the notes of whoever had worked on them. Dan asked for the tracking to be structured properly. This entry records how, and why.
What was decided, and by whom
Dan decided the shape, on 14 October 2026:
- One epic per machine: the KIM-1 (#99), the BBC Micro (#26), the NES (#100), the Electron (#51) and the Atari 2600 (#98, new). An existing issue was reused where it already was the machine’s tracking issue, so #26 and #51 became epics rather than gaining a twin.
- Three cross-cutting epics: Site and CI (#102), Speed (#103) and Models (3D) (#28, reused for the same reason). A fourth, Machines to come (#101), was added to hold the ranked list of machines after the Atari 2600 (#122), which had nowhere else to go.
- The 3D models’ re-work is parked at low priority under Models (3D): the NES’s #78 and #79, and four new issues for the BBC Micro’s gaps (#110 to #113). Each says what a re-try needs: a new check, fixed before it runs, because the old checks’ failures have been diagnosed and a method could now be tuned to them.
- The Atari 2600’s design was settled in an interview the same day and is written up in its own spec pull request (#104, entry
2026-10-14-the-atari-2600-design.md). Its tracking issue is #105, and the four parts the spec leaves out or depends on are filed under #98 and blocked by it.
Chosen over: one epic per kind of work (machines, site, speed) with the machines as labels. Rejected because each machine is a unit of work that ends (its registry row counts), and the epic is where “done” for that machine is written down.
How it is kept
The repository opts into Dan’s deskwork skill, configured in .github/deskwork.toml. It files issues from a template (Context and Acceptance for a Task; Expected and Actual added for a Bug; Proposal and Out of scope for a Feature), checks for duplicates before filing, records each blocker with its reason in a comment on the issue, and writes roadmap.md from an order given with a reason for each item.
- Sub-issues are the source of truth for what an epic holds. Each epic’s body says its status and what “done” means, and names its children for a reader, but the sub-issue list is what counts.
- Labels:
epicmarks the nine epics.priority:lowmarks what is parked. The machines keep their own labels, andatari-2600was added. The skill’s area labels (area:core,area:ci,area:models,area:speed,area:rights) are kinds of work that cut across machines; the machines were not repeated as areas, because two labels for one machine would drift. - Triage: the skill puts
triageon every issue it files. It was taken off the issues Dan named, because he had already decided them, and left on the two found in the notes and filed on judgement (#120, a stray character on the KIM-1’s teletype paper, and #121, whether the committed GPL disc fits rule 3), for Dan to read. - Issue types: Bug, Feature and Task, the organisation’s three. The epics are Features.
What was checked
The live list of open issues was read before anything was moved (gh api repos/dbhq-uk/6502/issues?state=open), and it had changed from the list in the brief: #91, the flaky NES panel wait, was already closed. After the moves, deskwork review --json showed every open issue under exactly one epic, and the epics under none.
The notes from the merge train of 13 and 14 October 2026 were read for anything not yet tracked. Each item found became an issue with its sources cited: the journal’s duplicate orders (#115), the site test floor held in two workflows (#116), the throwaway CI branches (#117), the BBC models’ camera that once did not settle (#118), the scans behind the BBC board’s track map (#119), and the two above.
Blockers, and what was not made a blocker
Each blocker was recorded with deskwork link and a reason. The four Atari 2600 issues are blocked by the spec (#105), because nothing for the machine is built before it merges. The ranked list (#122) is blocked by the Atari 2600 epic, because its acceptance waits for that machine to count. Three proposed edges were rejected and recorded as rejected, so they are not proposed again: the NES’s scanline renderer (#72) and lazy APU (#73) are options that #67 lists, not work #67 must finish first, and the BBC Micro’s copper re-trace (#111) does not wait for the NES’s (#78).
Not done, and why
- The board. Dan asked for a Projects v2 board as well. The token lacked the
projectscope at first. Later the same day the account was switched (the old namedandcghad been renamed togrinidx) and logged in again with the scope, and the org board “6502” (https://github.com/orgs/dbhq-uk/projects/1) was made, linked to this repository, and its node id put in.github/deskwork.toml.deskwork initadded the Triage option to Status, so its options are GitHub’s three (Todo, In Progress, Done) plus Triage, not the five first planned (Backlog and Next were left out: the roadmap file says what is next).deskwork intakethen put all 89 open issues on the board anddoctorreported no drift. The count of 89 is the day’s count, from the roadmap’s first line, not a claim about now. - A mistake, caught. Two issues filed one after the other (#117 and #118) had their labels and their places in the roadmap’s order swapped by number. Reading each title back found it before the roadmap was written, and both were corrected.
- Nothing was closed, assigned or prioritised beyond the labels above. #44 stays open: its last item, five wording nits from a review, was never written down and cannot be recovered, and a comment on it says so.
Later the same day: the Atari 2600’s issues, as its spec lists them
Dan answered the Atari 2600 spec’s questions and its pull request (#104) merged. Three answers changed what had been filed in the morning. The Superchip variants (F8SC, F6SC and F4SC) are in the first version, so they are not a not-modelled issue. Both test forks now exist in dbhq-uk, so the fork issue (#109) is done and a comment on it says so; it stays open for Dan to close. The bundled game is 2048 2600, with Core Escape as the fallback.
The spec’s section “Forks and issues” asks for an issue per part it leaves out, finer than the morning’s split, and those were filed under the Atari 2600’s epic (#98): the paddles (#108, retitled from the morning’s issue that held all three controllers), the keypads, the driving controller, other peripherals, the analogue picture with PAL colour loss, detecting the board from the image, the speed pass and the 3D models (#124 to #130). The speed pass and the models sit under the machine’s epic, with the labels area:speed and area:models, rather than under Speed or Models (3D), so that the machine’s epic holds all of its work. The bank switching issue (#107) became the parent of one issue per board not modelled (#131 to #155), each naming its tests in the suite where it has them, all at low priority.
Every one of them is blocked by the spec issue (#105), because nothing for the machine is built before its spec merges. The spec has now merged, and a comment on #105 says its acceptance looks met; closing it is Dan’s, and it unblocks them.